|  >Top Glossary:
              0.6 Power Law5E and 2A 6C of Community7P of MarketingABC = Activity Based Costing AC = Actual CostACWP = Actual Cost of Work Performed AD = Activity Description ADM = Arrow Diagramming MethodAF = Actual Finish DateActive ListeningAOA = Activity-On-ArrowAON = Activity-On-NodeAPQC = American Productivity & Quality Center AS = Actual Start DateAssumptions analysis BAC = Budget At Completion Backward Pass BaselineBCWP = Budgeted Cost of Work PerformedBCWS = Budgeted Cost of Work Scheduled BSC = Balanced ScoreCard Calendar Unit CAP = Control Account PlanCCB = Change Control BoardChart of Accounts ChaosCMMI = Capacity Maturity Model Integrated (= ISO/IEC 15504)COBIT = Control Objectives for Information 
                and related TechnologiesCOBIT Maturity ModelCommunicationContextContingency Planning Contingency Reserve >TopContract
ControlControl Chart Core CompetenceCOSO = Committee of Sponsoring Organization of the Treadway CommissionCost of Quality CPFF = Cost Plus Fixed Fee CPI = Cost Performance IndexCPIF = Cost Plus Incentive Fee CPM = Critical Path MethodCPO = Chief Project OfficerCSF = Critical Success FactorCSO = Chief Strategic Officer CV = Cost VarianceDD = Data Date CrashingDebt Equity RatioDecision Tree Analysis DeliverableDomainDU = DurationDummy Activity EAC = Estimate At CompletionEF = Early Finish DateEffortEPC =Engineering , Procurement & Construction ES = Early Start DateETC = Estimate to CompleteEV = Earned ValueEVM = Earned Value Management Exception Report ExitExpected Monetary Value Fast Tracking  >Top FF = Finish-to -Finish
FFP = Firm Fixed PriceFFIF = Fixed Price Incentive FeeFloatFMEA = Failure Mode & Effects Analysis Forward Pass Front End PlanningFS = Finish-to-StartFTA = Fault Tree Analysis Function Points Method GERT = Graphical Evaluation & ReviewGradeHammockHangerIDEFIFB = Invitation For BidID = Influence DiagramInitiationIRR = Internal Rate of Return ITIL = IT Infrastructure Library IT MaturityKGI = Key Goal Indicator KPI = Key Performance Indicator LagLeadLessons Learned LFD = Late Finish DateLOE = Level of EffortLogical RelationshipLoopLot Factor LSD = Late Start DateMECE = Mutually Exclusive, Collectively Exhaustive Milestone ScheduleMissing links of IT failureMission (6W1H) Monte Carlo Analysis  >TopMonitoring
Moral Hazard MPM = Modern Project ManagementNodeOBS = Organizational Breakdown Structure Organizational Planning Parametric Estimating Pareto Diagram Pass ConvergencePayback Period PC = Percent CompletePerforming Organization Phased Termination ReviewPM TheoryPredecessor Activity PDM = Precedence Diagramming MethodPERT = Program Evaluation and Review TechniquePFD = Planned Finish DatePFI = Private Finance Initiative PMP = Project Management ProfessionalPPM = Product Portfolio ManagementProbability and Impact Matrix Project Charter PSD = Planned Start Date PV = Planned ValueQA = Quality Assurance RAM = Responsibility Assignment Matrix RDU =Remaining DurationReal Option Residual RiskResource Leveling  >TopResource-Limited Schedule
RetainageRework RFP = Request For ProposalRFQ =Request For QuotationRiskRisk Database Risk Event Risk Management Plan Risk MitigationRisk Transference SBU = Strategic Business Unit ScenarioScope PlanningS-CurveSECI = Socialization, Externalization, Combination, InternalizationSensitivity AnalysisSF = Start-to-FinishShould-Cost EstimateSix Sigma SMART = Specific, Measurable, Agreeable, Realistic, Time boundSolicitationSPA = Software Process AssessmentSPI = Schedule Performance IndexSPDLI = Strategy, Plan, Do, Learning, InnovationSS = Start-to-StartStakeStructured Walk-throughSV = Schedule VarianceSWOT = Strength, Weakness, Opportunity, ThreatTaskT&M = Time and Material contracts TCD = Target Completion Date TFD = Target Finish Date TQM = Total Quality Management TriggerTSD = Target Start Date Value Proposition >TopVE = Value Engineering
WBS = Work Breakdown StructureWorkaroundWork Item Work Package  | *Source: 
            mostly from PMBOK guide (2000 version) , 
              P2M guide book (2001) , COBIT, ITC Process Guideline, Wikipedia,etc. 
              0.6乗則:一般的に生産設備など生産プロセスが変わらない場合、建設コストはベキ乗比例に依って変動する。n=0.6を適用する生産設備が多い。5E + 2A for Assessment: Efficiency, Effectiveness, Earned Value, 
                Ethics, Ecology, and Accountability, Acceptability 6C:Communityの人間・情報・文化的な属性には、Context (全体に共有する意義), Creativity, Collaboration, 
                Communication, Contents, Concentrationがある。マーケティングの7P:Product (製品), Price (価格), Place (チャネル), Promotion (販売促進), 
                Promise (顧客の信頼), Provider (サポート), Performance (顧客満足度)活動基準原価計算:Robert S. Kaplan & Robin Cooperによるコスト計算法の一つ。活動が資源を消費し、製品が活動を消費するという二段階の配賦を行う。多品種少量生産時代の間接費配賦を正確化した。Activityに応じてCost 
                driverを決めて活動の間接費を計測する (例:営業訪問回数)。Cf: ABM (Activity Based Management)実コスト (Total costs budgeted within the planned value and earned 
                value)作業完了実コスト、実績コスト (= now replaced with the term Actual Cost)アクティビティ記述 (The activity description normally describes the scope 
                of work of the activity.)00アロー・ダイヤグラム法 (The tail of the arrow represents the start, and the 
                head represents the finish of the activity. The length of the arrows 
                does not represent the expected duration of the activity. Activities 
                are connected at points called nodes to illustrate the sequence 
                in which the activities are expected to be performed.)実終了日アクティブ・リスニング (傾聴)アクティビティ・オン・アローアクティブティ・オン・ノード米国生産性品質センターの標準的なビジネスプロセスモデル:7つの基幹業務プロセス (顧客・戦略策定・設計・販売・生産出荷・サービス・代金回収)と6つの支援業務プロセス 
                (人材・情報・財務・環境・生涯・改革)から成る。実開始日前提条件の分析 (explores the assumptions' accuracy and identifies risks 
                to the project from inaccuracy, inconsistency, or incompleteness 
                of assumptions.)完成時総予算復路時間計算 (The calculation of late finish dates and late start dates 
                for the uncompleted portions of all network activities. Determined 
                by working backwards through the network logic from the project's 
                end date.)ベースライン (The original approved plane for a project, a work package, 
                or an activity)完了作業予算コスト、出来高 (Now called EV) 予定作業予算コストバランススコアカード (introduced by Robert 
                Kaplan & David Norton in 1992. It balances a financial perspective 
                with customer, internal process, and learning & growth perspectives.)):財務、顧客、業務 
                (内部プロセス)、人材 (学習と成長)の4つの視点からバランスよく評価する。過去 (財務)、現在 (顧客・内部プロセス)、未来 
                (学習と成長)カレンダー単位 (The smallest unit of time used in scheduling the project; 
                hours, days, or weeks, or even in minutes.)コントロール・アカウント・プラン (Previously called a Cost Account Plan. A management 
                control point where the integration of scope, budget and schedule 
                takes place, and where the measurement of performance will happen.)変更管理委員会 (A formally constituted group of stakeholders responsible 
                for approving or rejecting changes to the project baselines.)勘定科目表 (Any numbering system used to monitor project costs by category; 
                e.g. labor, supplies, materials, and equipment.)カオス:周期性を持たず、一見、不規則かつ乱雑な挙動を示す軌道をもつ系をいう。ソフトウェア能力成熟度モデル:プロセス改善の国際標準でベンダーの成熟度を示す。CMMの後継。CMM V1.0は1987~1997、CMM 
                V1.1は2002に、CMM V1.2は2006.8にリリース。CMMIはSEI (Software Engineering Institute)が策定した総合的指標。ITガバナンス実践規範 (COBIT):ISACA (Information 
                Systems & Audit Association)が決めたITを管理するためのオープンスタンダード。CSF, KGI, 
                KPIを定めている。 34のITガバナンス領域について6段階の成熟度で評価する。PO=Plan & Organize, 
                AI= Acquire & Implement, DS=Delivery & Support, ME=Monitor 
                & EvaluateCOBITの6つの成熟度モデル:Level-0: Non-existent 存在しない, Level-1: Initial 
                初歩的, Level-2: Repeatable 反復可能, Level-3: Defined 定義された, Level-4: 
                Managed 管理された, Level-5: Optimized 最適化されたコミュニケーション:1) 他者を理解し、理解されようとする過程の動き、2) 言語シンボルを通じて反応を引き出す過程、3) 記号を選択し、創出、伝達することで、伝達者が意図した意味を受け手が近くできるにする過程。コンテキスト:コミュニケーションに影響する物理的、社会的、心理的、時間的な環境を指す。コンティンジェンシー計画 (特定リスク事象の場合でもプロジェクトを成功させる代替戦略)コンティンジンシー予備 (リスクに対応するプロジェクト上乗せ金額や時間)契約:調達には、定額請負契約 (一括請負)、実費償還契約、単価契約のいずれか、またはこれらの組合せの契約形態がある。コントロール (Process of comparing actual performance with planned performance, 
                analyzing variances, evaluation possible alternatives, and taking 
                appropriate corrective action as needed)管理図 (A graphic display of the results, over time and against established 
                control limits, of a process. it is used to determine if the process 
                is in control or in need of adjustment.)コア・コンピタンス戦略:Garyt Hamel, C.K. Prahaladが定義。既存のCC × 既存市場=レバレッジ戦略、既存CC 
                × 新規市場=空白エリア、新規CC × 既存市場=プレミアムプラス10、新規CC × 新規市場=巨大なビジネスチャンス米国トレッドウェイ委員会内部統制フレームワーク品質コスト (The cost incurred to ensure quality. )コスト・プラス固定費 (The buyer reimburses the seller for the seller's allowable 
                costs, and the seller earns its profit if it meets defined performance 
                criteria.)コスト効率指数 (実コストに対比したEVのコスト効率; CPI = EV / AC)コスト・プラス・インセンティブフィー (Allowable cost + Incentive) クリティカルパス法 (to predict project duration 
                by analyzing which sequence of activities has the least amount of 
                scheduling flexibility. Early dates are calculated by means of a 
                forward pass, using a specified start date. Late dates are calculated 
                by means of a backward pass, starting from a specified completion 
                date.)重要成功要因:COBIT定義のITプロセスを成熟度レベル毎に適正に実行するための成功要因。チーフ・プロジェクト・オフィサー、プロジェクト総括責任者経営戦略責任者:IT戦略を統轄し、経営を支援する責任者。日本ではまだ少ない。コスト差異 (CV = EV - AC) データ日付 (The date at which, or up to which, the project's reporting 
                system has provided actual status and accomplishments. Also called 
                as-of date.)クラッシング(最小コストで、最大の所要時間短縮)債務資本比率:負債の自己資本に対する比率。この比率が高いとレバレッジ度は高くなり、財務内容が不安定化する。デシジョンツリー分析 (incorporates probabilities or risks that the costs 
                or rewards of each logical path of events and future decisions.)要素成果物 (Any measurable, tangible, verifiable outcome, result, or 
                item that must be produced to complete a project.)ドメイン:Derek.F. Abelの定義:ドメインには顧客の軸 (市場)、技術の軸、機能の軸3つの決定要因がある。どのような顧客に対し(whom)、どのような技術をもって(how)、どのような利便性・満足(what)を提供していくのかCustomer, 
                Technology, Functionを定義。それぞれの軸に対し、特化戦略 (少数セグメント対象 Niche player)、差別化戦略 
                (事業内の差別化 Challenger)、非差別化戦略 (広範囲に事業展開 Leader)、さらに経済性・模倣戦略(Follower)所要時間ダミー・アクティビティ (An activity of zero duration, which is used when 
                logical relationships cannot be completely or correctly described 
                with regular activity arrows.)完成時総コスト見積最早終了日作業工数 (人・時、人・日など) (The number of labor 
                units required to complete an activity.)ターンキー契約。プラント契約などで、設計、調達、据付工事までの一括請負契約という。最早開始日残作業コスト見積、今後必要コストアーンド・バリュー (The physical work accomplished, per the authorized 
                budget for this work. The sum of the approved cost estimates for 
                activities. Previously called the budged cost of work performed, 
                BCWP)アーンド・バリュー・マネジメント (It compares the amount of work that was planned 
                with what was actually earned and with what was actually spent to 
                determine if cost and schedule performance are as planned.)例外報告書 (Document that includes only 
                major variations from plan, rather than all variations.)退出:プロジェクトの終了(Close Out)をプロジェクト主体の立場からExitと呼ぶ。任意の時点でExitできることを意味する。期待金額値 (発生確率×損失額) ファスト・トラッキング (Compressing the project schedule by overlapping activities 
                that would normally be done in sequence, such as design and construction. 
                CFM: concurrent engineering)終了ー終了関係完全定額定額インセンティブフィーフロート (The amount of time that an activity may be delayed from 
                its early start without delaying the project finish date. CFM. Slack) 
                アクティビティまたはパスが所要期間から遅延した場合に、他に影響を及ぼさない余裕のこと。全体フロート (全体の余裕) と自由フロート 
                (個々の余裕) とがある。故障モード影響解析:設計の不完全性や潜在的欠点を見出すために構成要素の故障モードとその上位アイテムへの影響をボトムアップ的に解析する技法フォワード・パス (往路時間計算) (the calculation of the early start and early 
                finish dates for the uncompleted portion of all network activities.)フロントエンド・プラニング:プロジェクトは時間経過とともに消費される資源は幾何級数的に増大し、蓄積された情報量も成果物も増大する。後ほどインパクトが大きくなる。従って、プロジェクト初期段階で、人を含む、より綿密な計画を作成する手法終了ー開始関係好ましくない事象について、その発生の経過に遡って樹形図に展開し、発生経路、発生原因、発生確率をトップダウン的に原因を解析する技法ファンクション・ポイント法:ソフトウェアの規模はソースコードの行数ではなく、実現される機能の数を基に算出する方法。あるソフトウェアのFunction 
                Point(FP)は、FP = K × (Pi+Po+Pq+Pf+Pe) となる。Piは入力数、Poは出力数、Pqはユーザからの問い合わせ数、Pfはデータとして利用されるファイル数、Peは外部インターフェイス数。ガート (ネットワーク分析手法の一つ)等級 (A category or rank used to distinguish items that have the 
                same functional use, but do not share the same requirements for 
                quality.)ハンモック (An aggregate or summary activity. A hammock may or may 
                not have an internal sequence.)ハンガー (An unintended break in a network path. Hangers are usually 
                caused by missing activities or missing logical relationships.)Integrated DEFinition: プロセスを相互作用するアクティビティの集合としてモデル化、関係を矢印で表現するシステムの分析手法入札招請書 (Equivalent to Request for Proposalインフルエンス・ダイヤグラム:競争優位を出発点として、収益をもたらし、それが投資の要素となり、活動レベルと結びつくことで、競争優位が得られる。矢印の始点が原因であり、終点が結果となるPositive 
                feedbackとなる。立ち上げ (Authorizing the project or 
                phase)内部収益率:その投資が稼働する各年毎に収益の現在価値の合計と投下した資本の現在価値とが等しくなるような利益率を求めることで、プロジェクトの可否を判断する。ITインフラストラクチャ・ライブラリィ:英国OGC=Office of Government Commerce が索敵したコンピュータシステムの運用管理業務に関する体系的なガイドライン。サービスサポートとサービスデリバリの2つの領域から構成。IT成熟度:= IT governance × IT literacy × IT environment × IT service 
                utilization 重要目標達成指標:何を達成するかを示す尺度重要成功業績評価指標:ITプロセスがどのように実行されるかを示す尺度ラグ (A modification of a logical relationship that directs a delay 
                in the successor task.)リード (A modification of a logical relationship that allows an acceleration 
                of the successor task.)教訓 (プロジェクト記録の一つ)最遅終了日間接作業 (Support-type activity; e.g. vendor or customer liaison that 
                does not readily lend itself to measurement of discrete accomplishment.)論理的順序関係 (A dependency between tow 
                project activities: 
                FS (Finish-to-Start): The initiation of work of the successor 
                  depends upon the completion of work of the predecessor. FF (Finish-to-Finish): The completion of the work of the successor 
                  depends upon the completion of work of the predecessor. SS (Start-to-Start): The initiation of work of the successor 
                  depends upon the initiation of the work of the predecessor. SF (Start-to-Finish): The completion of the successor depends 
                  upon the initiation of the predecessor.  ループ (A network path that passed the same node twice. Loops cannot 
                be analyzed using traditional network analysis techniques. loops 
                are allowed in graphical evaluation and review technique.)ロットファクター:製品調達で、多数個注文した方が安価になることをいう。最遅終了日ミーシー:論旨思考のルール:相互に排他的で重複が無く、かつ全体が網羅されていること。マイルストーン・スケジュール (A summary-level schedule that identifies the major 
                milestones.)IT失敗のミッシング・リンク:1) 経営改革とIT活動の乖離、2) IT活動の各段階の分断、3) 利害関係者のdiscommunicationミッションの表現:Who (所有者), What (問題と解決), When (始まりと終わり), Why (意義), How 
                (エンジニアリング), Which (方向性・選択), Whom (ステークホルダ) モンテカルロ法 (to perform a project simulation many times to calculate 
                a distribution of likely results.)監視 (Capture, analysis, and reporting of project performance, usually 
                as compared to plan) モラルハザード:貸し手と借り手の情報が非対称的である場合、借り手がその立場を利用して、金融貸借において有利な行動をとるリスクをいう。広義には倫理観の欠如。モダン・プロジェクトマネジメント (A term used to 
                distinguish the current broad range of project management; scope, 
                cost, time, quality, risk, etc.)ノード (A junction point joined to some or all of the other dependency 
                lines.)組織ブレークダウン・ストラクチャ組織計画 (プロジェクトでの役割、責任、報告関係を文書化)係数見積 (実績データと変数との統計関係を用いた見積)パレート図 (A histogram, ordered by frequency of occurrence)パス収束 (The node in the schedule where parallel paths merge or join. 
                At that node, delays or elongation of any converging path can delay 
                the project.)回収期間:プロジェクト投資の回収期間を、予想されるキャッシュフローの総和が初期投資に等しくなる期間を指す。その後のキャッシュフローや金の現在価値など考慮しないシンプルな投資回収算出法。出来高パーセント母体組織 (The enterprise whose employees are most directly involved 
                in doing the work of the project.)フェーズ終了時レビュー:下流のフェーズへの移行をスムーズに行うために、そのフェーズの成果物を対象に実施されるレビュー。PM理論:リーダーシップの類型化。集団機能は、P機能 (Performance、叱咤激励) とM機能 (Maintenance、ねぎらい)とから成る。生産性は、短期的にはPM>Pm>pM>pmだが、長期的にはPM>pM>Pm>pmと言われる。先行アクティビティ (Activity that enters a node, or 'from' activity)プレシデンス・ダイヤグラム法 (Activities are linked by precedence relationships 
                to show the sequence in which the activities are to be performed.)パート (遂行評価図)計画終了日PFI、公共施設の整備のための資金調達。完工後の運営も民間委託することで、財政負担を軽減する。PPP = Public & 
                Private Partnershipともいう。 プロジェクト・マネジメント・プロフェッショナルプロダクト・ポートフォリオ・マネジメント:市場の成長率を縦軸に、市場シェアを横軸にとり、SBUをプロットする。1) 低成長シェア大:金のなる木 
                Cash cow、2) 低成長シェア小:負け犬 Dogs、3) 高成長シェア小: 問題児 Question mark、4) 高成長シェア大:花形製品 
                Star。負け犬は撤退し、金のなる木からの収益を問題児に投入し、花形に育てる投資戦略。発生確率影響度マトリックス (to determine whether a risk is considered low, 
                moderate, or high by combining the two dimensions of a ris1k, its 
                probability of occurrence, and its impact on objectives if it occurs.)プロジェクト憲章 (A document issued by senior management that formally 
                authorizes the existence of a project.)計画開始日計画価値品質保証責任分担マトリックス残余期間 (アクティビティの残余部分を完了するのに必要な時間)リアルオプション法:従来のNPV法が、投資案件を現在価値だけで捉え、過小評価しがちなのに対し、これは投資の延期、拡大縮小、撤退といった意思決定の柔軟性や選択権をも価値として捉え、投資案件全体の価値を評価する特徴がある。オプション行使による柔軟な対応:延期 
                (Postpone)、拡大 (Expand)、縮小 (Contract)、撤退 (Abandon)、段階 (Time to Build)、転用 
                (Transfer)、中断 (Shutdown & Restart)、解約 (Cancellation)  残余リスク (リスク対応策実施後も残存するリスク)資源平準化 (スケジュールを資源管理を考慮して行うネットワーク分析の一つ)制限制約型スケジュール留保金 (A portion of contract payment that is held until contract 
                completion to ensure full performance of the contract terms.)手直し (Action taken to bring a defective 
                or nonconforming item into compliance with requirements or specifications.)提案依頼書見積依頼書リスク:f(リスク事象 Risk event × 発生確率 Probability × インパクト Amount at stake)リスクデータベース (An output of the risk monitoring and control process.)リスク事象 (A discrete occurrence that may affect the project for better 
                or worse.)リスク・マネジメント計画書 (Documents how the risk management processes will 
                be carried out during the project. The output of risk management 
                planning.)リスク軽減 (to reduce the probability and/or impact of a risk to below 
                an acceptable threshold.)リスク転嫁 (to shift the impact of a risk to a third party together 
                with ownership of the response.)戦略的事業単位:事業単位がマネジメントの観点からの組織単位に対し、同一の事業特性をもつ事業 (製品群)を基に全社的な戦略実現の観点から再設定した組織単位。Cf: 
                Product portfolio シナリオ:現状(As-is)からあるべき姿(To-be)へのストーリとして描く表現形式。問題設定 
                (Issue setting)、問題解決の教示 (Solution implication)、実現の道筋 (Roadmap)、方法論(Methodology)、その効果(Performance)スコープ計画 (プロジェクト作業を段階的に詳細化するプロセス)Sカーブ (Graphic display of cumulative costs, labor hours, percentage 
                of work, etc; flatter at he beginning and end, steeper in the middle) 
                Cf: Front End Planning SECIモデル:野中郁次郎理論:Socialization (共同化=暗黙知を獲得伝達), Externalization 
                (表出化=暗黙知を形式知化), Combination (連結化=形式知同士を組み合わせて新たな形式知を創造), Internalization 
                (内面化=利用可能な形式知を個人が実践し、暗黙知として体得)感度分析:合理的な前提条件の下での経済性評価(Base Case)に対し、前提条件が変化した場合、Base Caseに対し、事業性やCash 
                flowへの影響を検討することをいう。 開始ー終了関係査定見積 (応札額の妥当性評価) (An estimate to provide an assessment of the 
                reasonableness of a prospective contractor's proposed cost.)シックス・シグマ:欠陥率を従来の3σ、4σから6σに改善することで、収益性、能力を向上させる経営手法。経営戦略のSMART:具体的 Specific、定量的 Measurable KGI, KPI、同意 Agreeable、現実的 
                Realistic、時間内 Time bound引合 (Obtaining quotations, bids, offers, or proposals as appropriate.)ソフトウェア・プロセス・アセスメント:ベストプラクティスと現状との乖離を把握するためのギャップ分析のためのSoftware 
                Process Improvement (SEI)。5つのフェーズ(IDEALモデル) から成る。初期 (Initiating)、診断 
                (Diagnosing)、モデル構築 (Establishing)、改善実行 (Acting)、展開 (Learning) スケジュール効率指数 (SPI = EV/PV)SPDLIサイクル:PDCAとは異なり、構造変革を含むサイクル。Planは実行計画ではなく変革計画である。またCheckでは変化に対応できないので、Learningプロセスを入れ例外事項の予測、戦略変更にも対応。短期のPDCAを内包する長期的成功を支えるダブルループ。ビジョン(what)も実行(how)も同時に遂行する(whathow)。開始ー開始関係ステイク:A piece of wood or metal >> Money or property risked 
                in a wager or gambling game; A share or an interest in an enterprise; 
                Personal interest or involvement. ストラクチャード・ウォークスルー:レビューの実施方法。成果物の担当者がプロジェクト関係者・有識者を集めて、その成果物の妥当性を評価するために実施される会議スケジュール差異SWOT分析:内部環境分析と外部環境の変化によるタスク (WBSに含まれない最下位の間接作業)タイム・アンド・マテリアル契約 (実費精算契約)目標完成日目標終了日総合品質管理:経営戦略から顧客満足向上、品質向上へとブレイクダウンしていくマネジメント手法トリガー (Risk symptoms or warning signs, indicators that a risk has 
                occurred or is about to occur.)目標終了日バリュー・プロポジション:事業の独自性のこと。類型としては、1) 業務の卓越性 Operational excellence、2) 
                緊密な顧客関係 Customer intimacy、3) 製品の優位性 Product leadership 価値工学 (Life cycle costの最適化)ワーク・ブレークダウン・ストラクチャ (A deliverable-oriented grouping of project 
                elements that organizes and defines the total work scope of the 
                project. Each descending level represents an increasingly detailed 
                definition of the project work.)迂回策 (リスクを避ける)作業項目=Activityワーク・パッケージ (A deliverable at the lowest level of the WBS.) |